A project is behind. What are your options and what does each cost?
Cut scope, add time, add people, or lower quality — and the fourth is a loan at a bad rate. Adding people to a late project usually slows it further, because they consume the time of those who know the system. Cutting scope is almost always the honest answer, and the work is deciding what with the person who owns the outcome.